QUERSTIONS

Quick-freezing cold storage installation project construction programme and process

  The installation project of quick-freezing cold storage is a complicated process, which needs to be carried out in strict accordance with the specifications to ensure the quality and safety of the cold storage. The following will introduce the construction programme and process of quick-freezing cold storage installation project.

  I. Pre-construction preparation stage

  Programme design and preparation: determine the location and size of the cold storage, develop a detailed construction programme. Design the layout of the refrigeration system to determine the location of the equipment inside the cold storage. Select appropriate insulation materials and construction materials, and make purchasing preparations.

  Site preparation: Clean up the construction site and ensure it is level and clean. Check the drainage condition of the site to ensure that the drainage system is smooth.

  Material preparation: Prepare the required heat preservation materials, construction materials and refrigeration equipment according to the design scheme.

Quick-freezing cold storage installation project construction programme and process插图

  Ⅱ. construction stage

  Foundation construction: carry out foundation treatment and foundation pouring to ensure that the foundation is firm and levelled.

  Building structure construction: install the wall and roof of the cold storage, and adopt the way of choosing reasonable materials and construction specification to build.

  Installation of heat preservation materials: laying and fixing of heat preservation materials to ensure that the heat preservation effect meets the requirements.

  Installation of refrigeration equipment: Installation of compressor, condenser, evaporator and other refrigeration equipment, connection of pipelines and electrical lines.

  Internal decoration: carry out the internal decoration of the cold storage, including ground treatment, wall decoration and so on.

  System debugging: debugging of the refrigeration system to ensure the normal operation of the equipment.

  III. Completion and acceptance stage

  Overall acceptance: conduct a comprehensive acceptance of the structure of the cold storage, heat preservation effect and operation of the refrigeration system.

  Performance test: carry out the performance test of cold storage temperature control and refrigeration effect to ensure that the design requirements are met.

  Document archiving: archive relevant construction drawings, equipment specifications, acceptance reports and other documents.

  Training and handover: train the operators of the cold storage for use and carry out the final handover.

  The above is the construction programme and process of the quick-freezing cold storage installation project, through the construction in strict accordance with the norms, can ensure the quality and safety of the cold storage, to meet the needs of food refrigeration and preservation. If you have such cold storage construction needs in the near future, HAOCOOL specialises in providing a complete set of cold storage engineering design, equipment, installation, after-sales integration solutions for large-scale food, medicine, cold chain logistics, chemical and other enterprises to provide cold storage construction services.